Core Viewpoint - The company announced an adjustment to the implementation schedule of its fundraising investment project, which will not materially affect its normal operations and existing project plans [1] Group 1: Project Funding and Progress - On November 30, 2022, the company raised 1.56 billion yuan from specific investors for a project aimed at producing 100,000 tons of power and energy storage battery foil and for supplementing working capital [1] - As of September 30, 2025, the cumulative investment in the project reached 690 million yuan, representing a progress rate of 57.46% [1] Group 2: Project Timeline Adjustment - Due to geological conditions, power supply support, and equipment supply issues, the project timeline has been delayed, with the expected operational date adjusted from December 31, 2025, to September 30, 2026 [1]
万顺新材:调整年产10万吨电池箔项目募集资金实施进度