Core Viewpoint - Guangdong Yuedian A (000539) announced that its subsidiary, Guangdong Yuedian Dapu Power Generation Co., Ltd., has successfully completed the 168-hour full-load trial operation of Unit 3 of the Dapu Power Plant Phase II project, officially commencing commercial operations on December 9 [1] Group 1 - The Dapu Power Plant Phase II project is a significant investment by the company, indicating its commitment to expanding its power generation capacity [1] - The successful trial operation of Unit 3 marks a key milestone in the project, contributing to the company's operational efficiency and revenue generation [1] - The commercial operation of this unit is expected to enhance the overall energy supply in the region, aligning with the company's strategic goals [1]
粤电力A:广东粤电大埔电厂二期工程项目3号机组投产