立新能源:和田地区100万千瓦独立储能项目预计年底并网

Core Viewpoint - The company is advancing the construction of a 1.2 million kilowatt independent energy storage project, with significant milestones set for completion in the coming years [1] Group 1: Project Details - The company is working on a 1.2 million kilowatt independent energy storage project [1] - The project includes a 1 million kilowatt energy storage project in the Hotan region, expected to be connected to the grid by the end of 2025 [1] - A 200,000 kilowatt project in the Kuitun region is planned to be operational by June 30, 2026 [1] Group 2: Current Operations - The company has already connected independent energy storage projects to the grid, which are currently in trial operation [1] - These projects are achieving a daily cycle of charging and discharging, with operational scheduling frequency meeting the levels estimated in the feasibility study report [1]