探索新模式,守好“钱袋子”
Ren Min Ri Bao·2025-12-14 21:45

Core Insights - The article highlights the successful implementation of a simplified bidding process for irrigation projects in rural areas, which has led to improved efficiency and cost savings for local governments [1][2]. Group 1: Project Implementation - The irrigation project in Yueshan Village, Fujian Province, adopted a "competitive selection" model to streamline the process, eliminating the need for budget reviews, bidding agents, and hiring supervisory units [1][2]. - A review committee composed of town and village officials, along with technical personnel, was established to select the construction contractor, which helped save on bidding agent fees [1]. Group 2: Cost and Time Savings - The new approach resulted in an estimated savings of approximately 5,500 yuan in construction costs for the irrigation project [2]. - The average construction time for pilot projects in rural areas has been reduced from around 3 months to approximately 2 months, with overall costs decreasing by about 10% [2].