中矿资源:公司纳米比亚20万吨/年多金属综合循环回收项目第一期火法冶炼工艺工程已于纳米比亚当地时间2025年12月15日建设完毕并成功点火试生产运营

Core Viewpoint - The company has successfully completed the construction and trial production of its first phase of the multi-metal comprehensive recycling project in Namibia, marking a significant milestone in its operational capabilities [2] Group 1: Project Development - The first phase of the pyrometallurgical process engineering for the 200,000 tons/year multi-metal comprehensive recycling project in Namibia was completed and successfully ignited for trial production on December 15, 2025 [2] - The treatment capacity for germanium zinc slag in this phase is 80,000 tons/year, and it will produce semi-finished products containing germanium zinc oxide fume [2] - The company plans to advance the production operations of the first phase in 2026 while also progressing with the construction of the second phase of the pyrometallurgical process engineering and the hydrometallurgical process engineering [2]