Core Viewpoint - The company announced a delay in the "Annual Production of 60,000 Tons of Energy-Level Titanium (Alloy) Material Full Industry Chain Project," extending the expected operational status from 2025 to 2026 due to design adjustments and long supply cycles for customized equipment [1] Group 1: Project Details - The total investment for the project is 7.2 billion yuan, with 1.704 billion yuan planned to be raised from fundraising [1] - As of November 30, 2025, the company has utilized 895 million yuan of the raised funds, leaving 795 million yuan unspent [1] - The delay is attributed to adjustments in design plans and equipment selection, but it is stated that this will not have a substantial adverse impact on project implementation or the company's operations [1]
安宁股份:年产6万吨能源级钛材料项目延期至2026年