蒙草生态:镶黄旗PPP项目提前终止及债务重组

Core Viewpoint - The company announced the early termination of a PPP project contract with the Xianghuangzhu Construction Bureau, involving a total project cost of 150 million yuan [1] Group 1: Project Financials - The total project cost is 150 million yuan, with 42.49 million yuan already paid and 107 million yuan remaining unpaid [1] - The Xianghuangzhu Construction Bureau will pay 71.76 million yuan by December 31, 2025, and 28.1261 million yuan by December 30, 2026, totaling 99.8861 million yuan [1] - The company will waive the remaining debt after receiving the total payments from the Xianghuangzhu Construction Bureau [1] Group 2: Project Transfer - The project transfer will be completed within 15 working days after the company receives the 71.76 million yuan payment [1]