福能股份(600483.SH):目前暂未开展电化学储能电站投资

Core Viewpoint - Fuzhou Energy Co., Ltd. has not yet initiated investments in electrochemical energy storage stations, focusing instead on ongoing pumped storage projects [1] Group 1: Pumped Storage Projects - The Mulan pumped storage project, with a capacity of 1.4 million kilowatts, is expected to pass the investment decision in February 2024, with a total construction period of 69 months [1] - The Hua'an pumped storage project, also with a capacity of 1.4 million kilowatts, is anticipated to receive investment approval in July 2024, with a similar construction timeline of 69 months [1] - The Nan'an pumped storage project, with a capacity of 1.2 million kilowatts, is projected to pass the investment decision in August 2025, maintaining the 69-month construction period [1]