Core Viewpoint - The company has not yet initiated investments in electrochemical energy storage stations but has ongoing projects in pumped storage hydropower with specific timelines for decision-making and construction duration [1] Group 1: Project Status - The company is currently developing three pumped storage projects: - The Mulan pumped storage project with a capacity of 1.4 million kilowatts is expected to pass investment decision in February 2024, with a total construction period of 69 months [1] - The Hua'an pumped storage project, also with a capacity of 1.4 million kilowatts, is anticipated to receive investment approval in July 2024, with a similar construction timeline of 69 months [1] - The Nan'an pumped storage project, with a capacity of 1.2 million kilowatts, is projected to have its investment decision made in August 2025, again with a construction period of 69 months [1]
福能股份:公司目前暂未开展电化学储能电站投资