Core Viewpoint - The company will conduct annual maintenance and upgrades on its lead smelting system and associated facilities starting December 9, 2025, leading to an estimated production halt of approximately 27 days [1] Group 1 - The maintenance period will involve comprehensive inspections and upgrades of the production system [1] - As of the announcement date, the company has completed all maintenance plans and will fully resume production operations on January 12, 2026 [1] - The company advises investors to pay attention to information disclosure media and investment risks [1]