波哥大地铁一号线第四列列车运抵首都
Shang Wu Bu Wang Zhan·2026-01-12 16:54
Core Insights - The Bogotá Mayor, Garcés, announced that the fourth train of the Bogotá Metro Line 1 has arrived in the capital and is now at the Bosa vehicle yard for testing [1] - The train departed from Qingdao, China, on December 3, 2025, and took over a month to reach Bogotá [1] - The overall construction progress of Line 1 is currently at 70.72%, with plans to receive a new train every 15 days until October this year [1] - The progress of the project has been significantly aided by the completion of the first 10 kilometers of elevated track, with an expected completion rate of nearly 90% by 2026, alongside dynamic testing of the trains [1]