Core Viewpoint - China Nuclear Power (601985.SH) announced that the first concrete pour for the nuclear island of Unit 1 of the Jiangsu Xuwei Nuclear Heating Power Plant, invested by its controlling subsidiary China National Nuclear Corporation SuNeng, is scheduled for January 16, 2026 [1] Group 1: Project Details - The Unit 1 of the Jiangsu Xuwei Nuclear Heating Power Plant utilizes China's independently developed "Hualong One" nuclear technology [1] - The rated power of the unit is optimized to 1,222 megawatts, compared to the previously disclosed 1,208 megawatts in the announcement numbered 2024-053 [1] - The design operational lifespan of the unit is set for 60 years [1] Group 2: Company Operations - Following the first concrete pour, the company will have 13 nuclear power units under construction, with a total installed capacity of 15,148 megawatts [1]
中国核电(601985.SH):江苏徐圩核能供热发电厂一期工程1号机组浇筑核岛第一罐混凝土