“十五五”首台核电机组,今日开工!

Core Viewpoint - China Nuclear Power Co., Ltd. announced that the first concrete pour for the nuclear island of Unit 1 of the Jiangsu Xuwei Nuclear Heating Power Plant Phase I is scheduled for January 16 [1] Group 1: Project Details - The Unit 1 of the Jiangsu Xuwei Nuclear Heating Power Plant utilizes China's independently developed "Hualong One" nuclear technology [1] - The rated power of the unit is optimized to 1,222 megawatts, compared to the previously disclosed rated power of 1,208 megawatts [1] - The design operational lifespan of the power plant is 60 years [1] Group 2: Company Operations - After the first concrete pour, the number of nuclear power units under construction controlled by China Nuclear Power will be 13, with a total installed capacity of 15,148 megawatts [1]