Group 1 - The construction project at Zhoushan Free Trade Center is utilizing BIM technology for precise control of key processes during the basement foundation construction [3] - The main structure construction is adopting a "cross + parallel" approach, allowing for simultaneous progress across different sections, which optimizes processes and improves efficiency [3] - The project team successfully completed the concrete pouring task for the pit bottom slab within four days, demonstrating effective teamwork and commitment [3]