Core Viewpoint - The company has announced its participation in the Zambia Sakanya PPP project, which is expected to generate stable income and enhance regional transportation efficiency and competitiveness [1] Investment Details - The total investment for the project is $76.1292 million, with the company holding a 90% stake [1] - The concession period for the project is 22 years [1] Project Timeline - JASWIN company will sign the general contracting agreement in June 2024 [1] - The road and associated works from Ndola to Sakanya, covering 17.26 kilometers, are scheduled for completion and operation by February 22, 2026 [1] - The Sakanya port project is partially completed, with supporting works progressing [1] - The roadbed from Sakanya to Mufulira is completed, with main and auxiliary works advancing in an orderly manner [1]
嘉友国际:投资赞比亚项目,恩萨公路段完工运营并收费