Core Viewpoint - The Bosnian Federal Highway Company is advancing the modernization of transportation infrastructure in the Una-Sana Canton, with the preliminary design of the expressway project connecting Bihać, Cazin, and Velika Kladuša to the Croatian border now completed [1] Group 1: Project Overview - The total length of the project is nearly 46 kilometers, divided into three segments aimed at improving infrastructure, enhancing traffic safety, and strengthening connections with Croatia and the EU [1] - The first segment from Bihać to Cazin is 17.9 kilometers long and will include the construction of 3 bridges and 2 tunnels [1] - The second segment from Cazin to Šumatac is 14.3 kilometers long, featuring 6 bridges and 1 tunnel [1] - The third segment from Šumatac to Velika Kladuša and the Croatian border is 13.4 kilometers long, with plans for 7 bridges and 2 tunnels [1] - A total of 7 interchanges are planned along the entire route [1]