第二艘国产大型邮轮完成坞内起浮

Group 1 - The second domestically produced large cruise ship "Aida Huacheng" has successfully completed the dock water injection and has floated [1] - After floating, the cruise ship will be moved to the front dock room for the inclination test, which is a core technical step in the ship's launch process, determining the vessel's weight and center of gravity, crucial for stability and passenger comfort [3] - The launch operation will last for seven days, followed by tests of lifeboat detachment and in-dock cruising to verify the performance of 18 large lifeboats and 2 rescue boats under normal and emergency conditions. The ship is scheduled to officially launch on March 20, enter system debugging and interior completion, and begin trial runs by the end of May, with delivery expected by the end of the year [5]