Core Viewpoint - The company, Asia Potash International, is making significant progress on its second and third 1 million tons/year potash fertilizer projects, with both projects entering the later stages of mining construction [1] Group 1: Project Progress - The second 1 million tons/year potash fertilizer project has completed the main inclined shaft (3) and is currently reinforcing the shaft and installing the belt transportation system [1] - The third 1 million tons/year potash fertilizer project is advancing in the electromechanical installation phase, as well as tunnel reinforcement and preparation for the mining area, following the completion of the inclined roadway, main inclined shaft, and two ventilation shafts [1] - The company aims to achieve production as soon as possible for both projects [1]
亚钾国际:第二个、第三个100万吨/年钾肥项目均已进入矿建工程后期阶段