Core Insights - The Bogotá Metro Line 1 project is progressing with the arrival of the second train, currently undergoing assembly and static testing, expected to be completed soon [1] - As of September 30, the overall progress of the Metro Line 1 project reached 64.85%, with the third train expected to arrive in Cartagena by the end of the month [1] - The project will benefit approximately 2.9 million residents across nine districts, including Bosa, Kennedy, and Santa Fe [1] - Bogotá's mayor, Garcés, met with representatives from the World Bank and the Inter-American Development Bank in Washington to discuss financing for the second phase of the Metro Line 1 project, with an expected loan of $1.485 billion to be disbursed by the end of 2025 [1] - Discussions also included the bidding progress for the second phase and financing for the second line [1] Company and Industry - The Bogotá Metro Line 1 project is being implemented by a consortium led by China Harbour Engineering Company, with trains manufactured by CRRC Changchun Railway Vehicles [2]
波哥大地铁一号线第二辆列车抵达首都