Core Insights - The article discusses the progress of the company's supercharging station construction, highlighting the current number of stations and future targets [1] Group 1: Current Progress - The total number of supercharging stations has increased from 2328 to 2330 [1] - The progress towards the goal of 2500+ stations by the i8 release date is at 78.01% [1] - There are 66 days remaining until the i8 release, with a progress value of 68.72% [1] Group 2: Daily Requirements - To meet the i8 release target, the company needs to build an average of 2.58 stations per day [1] - For the goal of over 4000 stations by the end of 2025, the company needs to build an average of 7.63 stations per day for the remaining 219 days of this year [1] Group 3: New Stations - Two new supercharging stations have been completed: one in Changsha, Hunan Province, and another in Ganzhou, Jiangxi Province [1] - The specifications for the new stations include a 4C × 6 configuration in Changsha and a 4C × 4 configuration in Ganzhou [1]
理想超充站2330座|截至25年5月26日