Core Viewpoint - The article discusses the progress of the company's supercharging station construction, highlighting the current status and future targets for the i8 release and the end of 2025 goals [1]. Group 1: Supercharging Station Progress - Total number of supercharging stations has increased from 2449 to 2451 [1] - Progress towards the goal of 2500+ stations by the i8 release is at 93.66% [1] - There are 46 days remaining until the i8 release, with a progress value of 78.20% [1] Group 2: Daily Requirements - To meet the i8 release target, the company needs to build 1.07 stations per day [1] - For the end of 2025 goal of over 4000 stations, the company has a current progress value of 31.85% [1] - With 199 days remaining this year, the company needs to construct 7.78 stations per day to meet the year-end target [1] Group 3: New Stations Built - Two new supercharging stations have been completed in Fujian Province and Hubei Province, each with a specification of 4C × 6 [1]
理想超充站2451座|截至25年6月15日