东方国信:内蒙古智算中心1号楼(共22MW)已于6月份交付
Zheng Quan Ri Bao Zhi Sheng· 2025-09-22 14:08
Core Insights - Dongfang Guoxin has confirmed that the first building of the Inner Mongolia Intelligent Computing Center (22MW) was delivered in June and has started generating revenue [1] - The second, third, and fifth buildings (totaling 68MW) are nearing installation completion and are expected to commence operations by the end of this year [1] - The fourth and sixth buildings (totaling 110MW) completed their main structure topping in August and are projected to be operational by the end of next year [1]