厦钨新能:拟投资2.37亿元建设氢能及功能材料项目
Xin Lang Cai Jing· 2025-11-18 09:21
Core Viewpoint - Xiamen Tungsten New Energy plans to invest 237.68 million yuan in the construction of a hydrogen energy and functional materials project, which will not significantly impact the company's financial status or operating results in the short term [1] Investment Details - The investment will be made by Xiamen Tungsten New Energy's wholly-owned subsidiary, Xiamen Tungsten Hydrogen Energy [1] - The project aims to establish a production line with an annual capacity of 5,000 tons of hydrogen materials and 7,000 tons of functional materials [1] - Funding for the project will come from the company's own funds and loans [1] Project Timeline - The construction period for the project is set at 26 months, with production expected to commence in January 2028 [1]