Workflow
超充站建设目标
icon
Search documents
理想超充站3080座|截至25年8月18日
理想TOP2· 2025-08-18 12:43
Core Viewpoint - The company is making progress towards its goal of establishing over 4000 charging stations by the end of 2025, with a current total of 3080 stations built as of mid-August 2025, indicating a completion rate of 59.52% for the year [1]. Group 1: Charging Station Development - The total number of charging stations has increased from 3077 to 3080, with a target of 4000+ stations by the end of 2025, leaving 920 stations to be built [1]. - The progress for new stations this year is at 59.52%, with 135 days remaining in the year [1]. - To meet the year-end target, an average of 6.81 new stations need to be built daily [1]. Group 2: New and Restored Stations - Two new charging stations have been established in Jiangsu Province and Tianjin, both with specifications of 4C × 4 [1]. - One station has been restored in Beijing, which is a testing station and not open to the public, with specifications of 2C × 3 and 5C × 1 [1].