理想超充站3201座|截至25年9月7日
理想TOP2· 2025-09-07 12:09
Core Insights - The company has achieved a total of 3,201 supercharging stations as of September 7, 2025, with a goal of exceeding 4,000 stations by the end of the year [1] - The progress towards the annual target shows an increase from 64.80% to 64.85%, indicating a steady pace in station construction [1] - To meet the year-end target, the company needs to complete an average of 6.95 stations per day over the remaining 115 days of the year [1] Summary by Sections - **Supercharging Station Construction** - The total number of supercharging stations has increased from 3,195 to 3,201 in a short span, reflecting ongoing expansion efforts [1] - Six new stations have been established across various provinces, including Hunan, Guangdong, Guizhou, Shandong, Yunnan, and Zhejiang, with different specifications for each [1] - **Progress Metrics** - The current progress towards the annual target is at 64.85%, with a time progress value of 68.49%, indicating that the company is slightly behind schedule [1] - The company has 799 stations left to build to reach its goal, emphasizing the need for accelerated construction in the coming months [1]
山西高速破0, 理想超充站3195座|截至25年9月2日
理想TOP2· 2025-09-03 06:46
来源 :北北自律机 25年09月02日星期二 理想超充 5 新增。 超充建成数:3190→3195座 基于2025年底4000+座目标 还剩805座 今年新增数进度值:64.36%→64.58% 今年剩余120天 今年时间进度值:67.12% 需每日 6.71 座,达到年底目标值 【附】5 座新增建成 湖北省 神农架林区 神农架5A景区 白玉兰森林酒店 为城市/景区乐园4C站,规格:4C × 6 湖北省 武汉市 武汉四新体育公园 为城市4C站,规格:4C × 6 江苏省 南通市 南通海安星湖001商业广场 为城市4C站,规格:4C × 6 山西省 长治市 襄垣停车区(二广高速广州方向) 为高速服务区5C站,规格:2C × 3 5C × 1 陕西省 榆林市 榆林金刚寺 为城市4C站,规格:4C × 6 加微信,进群深度交流理想实际经营情况与长期基本面。不是车友群。 ———————————————————— ...
理想超充站3190座|截至25年9月1日
理想TOP2· 2025-09-02 06:35
来源 :北北自律机 25年09月01日星期一 理想超充 16 新增。 超充建成数:3174→3190座 基于2025年底4000+座目标 还剩810座 今年新增数进度值:63.66%→64.36% 今年剩余121天 今年时间进度值:66.85% 需每日 6.69 座,达到年底目标值 安徽省 合肥市 合肥金泉小区北门 为城市4C站,规格:4C × 6 北京市 朝阳区 北京望京万象汇 为城市5C站,规格:4C × 6 5C × 2 广东省 揭阳市 金和服务区(汕湛高速汕头方向) 为高速服务区5C站,规格:5C × 4 广东省 揭阳市 金和服务区(汕湛高速湛江方向) 为高速服务区5C站,规格:5C × 4 广东省 深圳市 深圳先科大院 为城市5C站,规格:5C × 4 广东省 湛江市 湛江恒福时代中心 为城市4C站,规格:4C × 6 广西壮族自治区 南宁市 南宁吾悦广场 为城市4C站,规格:4C × 4 海南省 海口市 海口日月广场南侧停车场 为城市5C站,规格:5C × 8 河北省 邢台市 ———————————————————— 【附】16 座新增建成 邢台宁晋唐朝酒店 为城市4C站,规格:4C × 4 江苏 ...
理想超充站3174座|截至25年8月31日
理想TOP2· 2025-09-01 07:50
Core Viewpoint - The company is progressing towards its goal of establishing over 4000 supercharging stations by the end of 2025, with a current completion rate of 63.66% for this year [1][2]. Group 1: Supercharging Station Development - The total number of supercharging stations has increased from 3161 to 3174, with 13 new stations added recently [1]. - The company needs to complete an average of 6.77 stations per day to meet the year-end target, with 122 days remaining in the year [1]. - The current progress towards the annual target is at 63.66%, while the time progress is at 66.58% [1]. Group 2: New Station Locations - New supercharging stations have been established in various cities, including: - Copper City, Anhui: 4C × 6 configuration [1]. - Chaoyang District, Beijing: 5C × 8 configuration [1]. - Shenzhen, Guangdong: 4C × 6 and 4C × 8 configurations [1]. - Nanjing, Jiangsu: Multiple 4C × 6 configurations [1][2]. - Other locations include Wuxi, Qingdao, Xi'an, and Wenzhou, with various configurations [2].
理想超充站3161座|截至25年8月30日
理想TOP2· 2025-08-31 09:43
Group 1 - The core viewpoint of the article highlights the progress of the company's supercharging station construction, with a current total of 3161 stations and a target of over 4000 by the end of 2025, indicating a remaining need for 839 stations to meet this goal [1] - The completion rate for new supercharging stations this year has increased from 62.87% to 63.09%, with 123 days left in the year, suggesting a need for an average of 6.82 new stations to be built daily to achieve the year-end target [1] - Five new supercharging stations have been established in various locations, including Hainan, Henan, Jiangsu, Shanxi, and Zhejiang, all categorized as urban 4C stations with varying specifications [1]
理想超充站3156座|截至25年8月29日
理想TOP2· 2025-08-30 08:58
Core Insights - The article discusses the progress of the company's supercharging station construction, highlighting the current number of stations and the target for the end of 2025 [1] Group 1: Supercharging Station Development - The total number of supercharging stations has increased from 3152 to 3156, with a target of over 4000 stations by the end of 2025, leaving 844 stations to be built [1] - The progress towards this year's target is at 62.87%, with 124 days remaining in the year, indicating a time progress value of 66.03% [1] - To meet the year-end goal, an average of 6.81 stations need to be constructed daily [1] Group 2: New Stations Added - Four new supercharging stations have been completed, including locations in Tianjin, Wuxi, Hangzhou, and Taizhou, with specifications varying from 4C to 5C configurations [1]
理想超充站3152座|截至25年8月28日
理想TOP2· 2025-08-28 16:01
【附】8 座新增建成 基于2025年底4000+座目标 还剩848座 今年新增数进度值:62.34%→62.69% 今年剩余125天 今年时间进度值:65.75% 需每日 6.78 座,达到年底目标值 北京市 顺义区 北京艾迪公园 为城市5C站,规格:5C × 8 广东省 东莞市 东莞天源电脑城 为城市4C站,规格:4C × 6 河北省 秦皇岛市 秦皇岛金梦海湾希尔顿欢朋酒店 为城市5C站,规格:5C × 8 来源:北北自律机 25年08月28日星期四 理想超充 8 新增。 超充建成数:3144→3152座 四川省 乐山市 理想汽车乐山长青路零售中心 为城市5C站,规格:5C × 8 云南省 昆明市 昆明阳光俊园 为城市4C站,规格:4C × 6 ———————————————————— 加微信,进群深度交流理想实际经营情况与长期基本面。不是车友群。 辽宁省 大连市 大连时代峯汇 为城市4C站,规格:4C × 6 内蒙古自治区 呼和浩特市 呼和浩特祥泰大酒店 为城市4C站,规格:4C × 8 陕西省 西安市 西安汇景国际广场 为城市5C站,规格:5C × 8 ...
理想汽车发布二季报 财务数据稳中向好
Cai Jing Wang· 2025-08-28 15:51
Core Viewpoint - Li Auto demonstrates strong operational resilience in a complex market environment, achieving significant growth in vehicle deliveries and profitability, marking it as the only new force car company with 11 consecutive quarters of profitability [1][12]. Financial Performance - In Q1 2025, Li Auto reported revenue of 25.9 billion yuan, a year-on-year increase of 1.1%, maintaining its position as the leading new force car company; net profit reached 647 million yuan, up 9.4% [2]. - Q2 2025 saw Li Auto's vehicle deliveries reach 111,074 units, with a net profit of 1.1 billion yuan [1]. - The operating profit for Q2 2025 was 827 million yuan, reflecting a year-on-year growth of 76.7% and a quarter-on-quarter increase of 204.4% [2]. Product Development and Market Position - The launch of Li Auto MEGA Home on April 23, 2025, led to it becoming the top-selling MPV over 500,000 yuan and the best-selling pure electric vehicle in the same price range [2]. - As of mid-2025, Li Auto's cumulative delivery volume reached approximately 203,800 units, with cash reserves exceeding 100 billion yuan, providing solid financial support for strategic transformation [5]. Research and Development - Li Auto invested 11.07 billion yuan in R&D in 2024, ranking among the top five Chinese car companies; Q1 2025 R&D expenses were 2.5 billion yuan, increasing to 2.8 billion yuan in Q2 2025, with a focus on artificial intelligence technology [6]. - The company achieved significant advancements in smart technology, including the development of the self-researched M100 auxiliary driving chip, expected to enhance driving assistance capabilities [7]. Technological Innovations - The VLA driver model, based on reinforcement learning, shows high accuracy in traffic signal recognition and spatial understanding, aiming to enhance AI's role in driving [9]. - Li Auto's self-developed silicon carbide power chips and modules are set to be integrated into its pure electric SUV models, showcasing its commitment to technological innovation [12]. Organizational Changes - In August 2025, Li Auto restructured its sales system, transitioning to a centralized management approach for 23 regions, enhancing decision-making efficiency and supporting multi-model sales [11]. - The company is undergoing a dual transformation from range-extended to pure electric vehicles and from regional management to centralized control, positioning itself for sustained growth [12].
理想超充站3144座|截至25年8月27日
理想TOP2· 2025-08-27 14:39
Core Insights - The company aims to achieve a target of over 4000 supercharging stations by the end of 2025, with a current count of 3144 stations, leaving 856 stations to be built [1] - The progress for new stations this year has increased from 61.94% to 62.34%, with 126 days remaining in the year [1] - To meet the year-end target, the company needs to build an average of 6.79 stations per day [1] Summary by Sections New Supercharging Stations - Nine new supercharging stations have been completed, including locations in Beijing, Guangdong, Guangxi, Ningxia, Shandong, Shaanxi, Tianjin, and Yunnan [1][2] - The specifications for the new stations vary, with some being 4C and others 5C, indicating different charging capabilities [1][2] Current Progress - The current progress towards the target of 4000+ stations is at 62.34%, with a time progress value of 65.48% for the year [1] - The company is on track but needs to accelerate the pace of new station construction to meet its goals [1]
理想超充站3135座|截至25年8月26日
理想TOP2· 2025-08-26 15:35
Core Insights - The article discusses the progress of the company's supercharging station construction, highlighting the increase in the number of stations and the targets set for the end of 2025 [1]. Group 1: Supercharging Station Construction - The total number of supercharging stations has increased from 3124 to 3135, with a goal of exceeding 4000 stations by the end of 2025 [1]. - The current progress towards the annual target is 61.94%, with 127 days remaining in the year [1]. - To meet the end-of-year target, an average of 6.81 new stations must be built daily [1]. Group 2: New and Restored Stations - A total of 21 new supercharging stations have been established across various locations, including cities in Henan, Sichuan, Tianjin, and Chongqing [1]. - One station has been restored in Gansu Province, specifically the Luotang service area [4].