南方电网储能股份有限公司关于募投项目南宁抽水蓄能电站投产的公告
Xin Lang Cai Jing· 2025-12-19 20:27
Core Viewpoint - The announcement highlights the commencement of trial operations for the first two units of the Nanning Pumped Storage Power Station, which is part of a significant asset restructuring project by the company, aligning with previously disclosed timelines for production [1]. Group 1: Project Details - The Nanning Pumped Storage Power Station has a total installed capacity of 4×300,000 kW [1]. - Units 1 and 2 have begun trial operations, while units 3 and 4 are expected to start trial operations by the end of the year [1]. Group 2: Compliance and Assurance - The company's board of directors guarantees that the announcement contains no false records, misleading statements, or significant omissions, and they assume legal responsibility for the content's truthfulness, accuracy, and completeness [1].
南网储能(600995.SH):募投项目南宁抽水蓄能电站投产
Ge Long Hui A P P· 2025-12-19 08:20
Core Viewpoint - Nanguang Energy (600995.SH) announced the significant asset restructuring and fundraising project for the Nanning Pumped Storage Power Station, with the first two units expected to enter trial operation by December 19, 2025, aligning with the projected commissioning timeline disclosed in the related report [1] Group 1 - The Nanning Pumped Storage Power Station has a total installed capacity of 4×300,000 kW [1] - Units 3 and 4 are expected to enter trial operation by the end of the year [1] - The units will officially commence commercial operation after completing the trial operation [1]
南网储能:募投项目南宁抽水蓄能电站投产
Ge Long Hui· 2025-12-19 08:09
格隆汇12月19日丨南网储能(600995.SH)公布,2025年12月19日,公司重大资产重组配套募集资金投资项 目南宁抽水蓄能电站(装机容量4×30万千瓦)1号、2号机组投入考核试运行,3号、4号机组预计将于 年底前投入考核试运行,符合公司《重大资产置换及发行股份购买资产并募集配套资金暨关联交易报告 书》披露的预期投产时间。机组将在完成考核试运行后,正式投入商业运行。 ...
广西首个抽水蓄能工程全面蓄水
Guang Xi Ri Bao· 2025-11-09 02:04
11月7日,记者从南方电网储能公司了解到,国家"十四五"重大工程南宁抽水蓄能电站上水库正式 启动蓄水,标志着工程建设进入全面蓄水阶段,为年内投产创造有利条件。 本次蓄水的成功启动,综合检验了南宁抽水蓄能电站上下水库以及输水、发电系统的整体性能,为 国内在建抽蓄工程树立了高效蓄水的新范式。作为广西首座抽水蓄能电站,该电站装机规模120万千 瓦,建成后每年最多可消纳清洁能源25亿千瓦时。(陆权香 黄昉) 启动上水库蓄水,是抽水蓄能工程的一个重要节点。针对南宁抽水蓄能电站上水库大坝前方存在40 米高坑的特殊库盆地形,项目部在国内首创"大流量抽水"加"小流量稳压"的蓄水方式——利用电站已并 网调试机组的抽水功能,将下水库的水以每小时约25万立方米的大流量迅速抽至上水库进出水口前池, 再利用吸水装置,将前池积水以每小时2000多立方米的小流量排入大坝基坑,待大坝底部受压稳定后, 再将水灌入整个水库。 据了解,南宁抽水蓄能电站下水库已于今年1月启动蓄水,上下水库总库容1340万立方米,相当于 近一个西湖的水量。电站投产前,上水库需蓄水约400万立方米。 ...
广西南宁抽水蓄能电站上水库工程通过蓄水前验收
Yang Shi Xin Wen· 2025-10-22 03:24
Core Insights - The Nanning Pumped Storage Power Station in Guangxi has successfully passed the pre-storage acceptance test and is scheduled to begin water storage by the end of October 2023, laying a solid foundation for full production by the end of this year [1][5]. Group 1: Project Overview - The total scale of the Nanning Pumped Storage Power Station is 1.2 million kilowatts, with a total investment of approximately 8 billion yuan [5]. - Once completed, the power station is expected to consume up to 25 billion kilowatt-hours of clean energy annually [5]. Group 2: Construction Innovations - The construction of the power station incorporates green and intelligent practices, significantly enhancing production efficiency [3]. - The water conveyance channel, over 3.5 kilometers long, was built using reinforced concrete lining, saving about 10,000 tons of steel compared to pure steel channels [3]. - The project utilized mechanized construction for the excavation of the self-draining tunnel, achieving a fourfold increase in efficiency compared to manual drilling [3]. - The upper reservoir area features China's first heavy-duty electric truck battery swapping station, utilizing 20 electric trucks for transporting earth and stone, saving 680,000 liters of fuel annually and reducing carbon dioxide emissions by 1,800 tons [3].