壹探轨道|重要建设进展!济南地铁4号线全线“轨通”!
Qi Lu Wan Bao· 2025-06-16 11:43
Core Points - The completion of the last pair of steel rails at the Shandong University East Road Station marks the full track connection of the Jinan Metro Line 4, laying a solid foundation for the line's opening by the end of this year [1][4] Group 1: Project Overview - The Jinan Metro Line 4 is a major east-west transportation artery in Jinan, with a total length of 40.3 kilometers and 33 stations [3] - The total length of the track laid is 85.074 kilometers, indicating a large-scale construction project [3] Group 2: Challenges and Innovations - The project faced multiple challenges, including long lines, tight schedules, dispersed work areas, frequent handovers, and complex environments [3] - To minimize environmental impact, the project team focused on overcoming technical challenges related to vibration and noise reduction [3] - A significant innovation was the optimization of the traditional cast-in-place spring floating slab track bed to a prefabricated assembly process, which improved construction precision and efficiency while reducing future noise levels by 10 to 14 decibels [3] Group 3: Construction Efforts - During peak construction, seven work fronts were opened simultaneously, utilizing three rail machines and 14 intelligent track-laying devices, with over 400 workers on round-the-clock shifts [3] - The project achieved a record of laying 670 meters of track in a single day through meticulous planning and dynamic optimization [3] - Safety and quality were prioritized throughout the construction process, with strict implementation of detailed control requirements [3][4] Group 4: Progress and Future Steps - The Jinan Metro Line 4 has successfully completed two major milestones: "tunnel completion" and "track completion," setting the stage for subsequent key phases such as electrical testing, joint debugging, and trial operations [4]
地铁2号线二期、5号线、7号线、9号线最新建设进度公布
Qi Lu Wan Bao Wang· 2025-06-16 06:44
Group 1: Metro Line 2 Phase II - The main structure of Longchuan Road Station has successfully topped out, achieving multiple records and completing the main structure 20 days ahead of schedule [3] - The station is part of the 8.9 km underground Line 2 Phase II, which connects the eastern part of Licang District with the city center and is expected to enhance transportation convenience for residents [3] Group 2: Metro Line 5 - The construction of the section between Changle Road Station and Eight Number Pier Station has achieved a breakthrough in shield tunneling technology under complex geological conditions, with a settlement control precision of 0.54 mm [5] - The completion of the protective pile construction at Lake Island Station has laid a solid foundation for subsequent excavation and structural work, finishing 69 days ahead of schedule [5] Group 3: Metro Line 7 - The main structure of all 7 stations in the second phase of Line 7 has been topped out, marking significant progress and multiple firsts in the construction timeline [6] - This line will facilitate rapid north-south connectivity, enhancing urban rail transit and boosting economic development along the route [6] Group 4: Metro Line 9 - The successful tunneling of the "Yongxing No. 1" shield machine under the墨水河 marks a record for the longest waterway crossing (130 meters) in the construction of Qingdao Metro Phase III [7] - The first phase of Line 9 is a key east-west backbone line in northern Qingdao, with a total length of 16.63 km and 13 stations planned [7]
济南轨道交通6号线山大南路站至茂岭山路站盾构区间双线贯通
Qi Lu Wan Bao· 2025-06-13 07:05
Group 1 - The construction of Jinan Metro Line 6 has reached a significant milestone with the successful completion of the double-line tunneling between Shanda South Road Station and Maoling Mountain Road Station, marking the "tunnel completion" from Dongcang Station to Liangwang Vehicle Base [2] - All 32 stations along Line 6 are currently under construction, with 29 stations having completed the main structure and 30 sections achieving double-line tunneling [2] - The geological conditions for the section between Shanda South Road Station and Maoling Mountain Road Station are complex, involving challenges such as high-strength boulders, construction debris, and various underground pipelines [2][3] Group 2 - The project team, consisting of China Railway Shandong Investment, Jinan Rail Transit Group, and China Railway No. 2 Engineering Group, has implemented meticulous planning and risk control measures to address the challenging construction environment [3] - Innovative techniques and precise control of tunneling parameters have been employed to ensure safety and efficiency during the construction process, particularly in the challenging areas under the Yaotoukou Bridge [3] - The successful tunneling through complex geological conditions has not only achieved a critical milestone but also provided valuable experience for future projects in similar challenging environments [3]
25号线全国首座全预制装配式矩形地铁车站 龙华公园站开始“搭积木”
Shen Zhen Shang Bao· 2025-06-13 00:05
Core Insights - The Shenzhen Metro Line 25 Phase I project has officially commenced the assembly of prefabricated components at Longhua Park Station, marking it as the first fully prefabricated rectangular metro station in the country, which will provide significant insights for industrialized construction in the metro sector [1][2] Group 1: Project Overview - The Line 25 Phase I project is a key component of Shenzhen's fifth-phase metro planning, stretching 16.5 kilometers with 14 stations, including 5 transfer stations and one vehicle depot [1] - Longhua Park Station is located at the intersection of Longguan Avenue and Longhua People's Road, featuring a two-level underground island station design with a total length of approximately 211 meters [1] Group 2: Construction Innovation - The project employs a rectangular fully prefabricated structural system, with major components such as the base slab, side walls, and roof being precisely prefabricated in a factory, with the heaviest component weighing up to 114 tons [1][2] - Advanced construction techniques include the use of a 180-ton gantry crane for high-precision lifting and an auxiliary cart for efficient assembly, resembling a "building block" approach [1] Group 3: Challenges and Solutions - The construction site faces significant challenges due to dense surrounding buildings, complex pipelines, and limited space [2] - To address these challenges, the company has implemented a millimeter-level precision control system for the gantry crane, along with intelligent positioning systems and hydraulic leveling devices to ensure high-precision placement of components [2] Group 4: Urban Impact - Upon completion, Line 25 Phase I will enhance connectivity with urban spatial structures and service core urban areas, supporting the development of key districts and improving transportation links for areas previously lacking rail access [2] - The project will also facilitate coordination with existing metro lines, maximizing network efficiency across the region [2]
壹探轨道|最新进展!济南地铁6号线2个区间双线贯通!
Qi Lu Wan Bao· 2025-06-12 14:49
Core Viewpoint - The construction of Jinan Metro Line 6 has reached significant milestones, with key sections successfully completed despite challenging geological conditions [1][9]. Group 1: Project Progress - The construction of Jinan Metro Line 6 has achieved double-line completion between Shanda South Road Station to Maoling Mountain Road Station and Jinan Station to Jiaan Street Station [1]. - All 32 stations along Line 6 have commenced construction, with 29 stations having their main structures topped out and 30 sections achieving double-line completion [1]. Group 2: Geological Challenges - The section between Shanda South Road Station and Maoling Mountain Road Station faces complex geological conditions, including soft upper layers of silty clay and hard lower layers of weathered diorite, along with high-intensity boulders and groundwater issues [3]. - The section from Jinan Station to Jiaan Street Station is characterized by unstable silty clay and gravelly silty clay, with some areas being water-rich, complicating the shield tunneling process [5]. Group 3: Innovative Construction Techniques - The project team has implemented a 24-hour leadership rotation system and conducted thorough investigations of surrounding buildings and pipelines to ensure safety and efficiency [5]. - Innovative techniques such as the earth pressure balance shield method and the "empty push over station" technology have been employed to enhance construction safety and efficiency [7][9]. - The use of "two initiations and two receptions" in tunneling operations has significantly reduced the impact on surface traffic and the surrounding environment [7]. Group 4: Future Implications - The successful completion of these sections not only addresses complex geological challenges but also sets a precedent for future shield tunneling projects in similar urban environments, providing valuable experience and techniques for broader application [9].
天津地铁8号线全线“洞通”
Zhong Guo Xin Wen Wang· 2025-06-12 00:42
Core Points - The Tianjin Metro Line 8 has achieved a significant milestone with the successful "tunnel completion" of its first phase and extension, laying a solid foundation for future operations [1] - This line is the first in Tianjin to utilize fully automated driverless technology (GoA4 level) and is equipped with a comprehensive smart operation and health management system [1] - The line spans 23 kilometers from Zhongbei Town Station in Xiqing District to Lushuidao Station in Jinnan District, featuring 21 stations and 21 sections, along with the construction of a new substation [1] Construction Challenges - The construction faced numerous world-class challenges, earning the title of "King of Challenges" in Tianjin's metro construction history, including five river crossings, three railway crossings, and seven existing metro crossings [1][2] - The project required coordination with seven other lines for transfers and reserved conditions for four future lines, with significant difficulties in land acquisition and protection of surrounding buildings and underground structures [1][2] - Special vibration reduction measures were implemented, with 65% of the line consisting of high-grade vibration reduction sections, and the Dawangfang Station being the deepest metro station under construction in Tianjin [1][2] Technological Innovations - The construction team utilized advanced technologies such as comprehensive geological radar detection, automated real-time monitoring systems, and precise settlement control techniques [2] - Innovative applications included soil improvement processes, optimization of shield tunneling parameters, and the establishment of emergency response mechanisms to overcome key technical bottlenecks [2] - As of now, all main structures of the 21 stations have been completed, and 17 out of 19 connection passages have been successfully finished, indicating steady progress in the project [2]
天津首条无人驾驶地铁全线洞通
Core Points - The Tianjin Metro Line 8 has successfully achieved "tunnel completion" for all shield sections, marking a significant milestone in the construction of the line [1][2] - This line is the first in Tianjin to utilize fully automated driverless technology and is designed as a major transportation backbone in the southern urban area [1] - The project is implemented through an integrated "investment-construction-operation" model by China Railway Construction Corporation, involving multiple construction units [1] Summary by Sections - **Construction Progress** - All 21 station structures have been completed, and all 21 sections are now connected, with 17 out of 19 connecting passages finished [2] - **Operational Impact** - Upon opening, the line will connect four administrative districts: Nankai, Heping, Hexi, and Jinnan, enhancing accessibility to key areas such as Anshan West Road and Wudadao [2] - The line is expected to serve as a new engine for urban development, providing a more convenient, efficient, and green travel experience for residents [2] - **Technological Features** - The line is equipped with a state-of-the-art fully automated driving system (GoA4 level) and a comprehensive intelligent operation and maintenance management system to ensure safe and efficient operations [1]
壹探轨道|济南地铁8号线中段“跑”起来了,全线调试即将启动
Qi Lu Wan Bao· 2025-06-05 13:41
Group 1: Jinan Rail Transit Line 4 - The construction of Line 4 has achieved "long rail connection" between the sections from Weilizhuang to Quancheng Park Station, marking a significant milestone in the project [1][5] - The project team has adopted an innovative "machine laying + manual laying" construction mode, which effectively addresses challenges such as limited space and multiple cross operations, achieving a record of 670 meters of track laid in a single day [4] - Key sections of Line 4 utilize steel spring floating slab track bed technology to reduce noise by 10 to 15 decibels, enhancing passenger comfort and ensuring smooth train operations [5][7] Group 2: Jinan Rail Transit Line 8 - The hot sliding test for Line 8 has officially started, which is a critical step before the full line dynamic debugging begins [8][10] - The dynamic debugging is expected to last for about 2-3 months, during which the performance and compatibility of various systems will be comprehensively tested and optimized [12] - All main structures of Line 8 have been capped, and decoration and auxiliary structure construction are progressing rapidly, with a goal to complete the line by the end of the year [12] Group 3: High New District Cloud Bus - The construction of the High New District Cloud Bus project is in the final sprint phase, with all 32 stations capped and decoration work underway [15] - Train debugging has already commenced between the Rainbow Lake Park Station and Tangye East Road Station, aiming for successful operation by the end of the year [15] Group 4: Noise Reduction Measures - In light of the upcoming high school entrance examinations, all ongoing projects are implementing a "silent action" to ensure a quiet environment for students, demonstrating the commitment to community welfare while accelerating construction [17]
济南轨交:已在社区、学校附近工地公布噪音投诉电话
Qi Lu Wan Bao Wang· 2025-06-04 06:03
6月1日至15日,集团所有在建工程(拆迁工地、建筑工地等)在中午12时至14时、夜间20时至次日6时, 不得进行产生噪声污染的施工作业。高考(6月7日至10日)和中考(6月13日至15日)期间,距居民区、距考 点500米范围内在建工程,除工程抢修、抢险外,停止一切产生噪声污染的施工作业。 "在敏感时段和区域设置噪声监督员,我们安排了人员实时巡查。还在工程周边社区、学校张贴《中高 考期间施工降噪措施告知书》,公布投诉电话。"路林海说。 齐鲁晚报.齐鲁壹点李梦瑶实习生陆明月 6月3日,"你赴考,我护航"2025济南城管静音护考"圆桌对话"专题圆桌对话举行。会上,济南轨道交通 集团安全监察部副部长石锦江表示,双考期间,济南轨交已在工程周边社区、学校张贴《中高考期间施 工降噪措施告知书》,公布投诉电话,以实际行动落实企业责任。 目前,济南轨道交通集团距考点500米范围内有11个在建项目,分布于历城区、天桥区、槐荫区、市中 区。双考静音行动启动后,轨道交通集团第一时间转发《关于加强中高考期间噪声污染防治的通告》, 同时,安全管控平台安排专人24小时值班,监测施工现场噪音分贝值,发现违规立即制止整改。 此外,集团成立专项 ...
重庆轨道交通15号线二期中梁山隧道贯通
news flash· 2025-06-03 11:40
重庆轨道交通15号线建设取得突破,二期控制性工程中梁山隧道顺利贯通。该隧道全长4944米,地质结 构复杂,施工过程中需穿越富水区、岩溶发育区和煤矿采空区等,中铁十四局采用超前地质预报等技 术,确保安全穿越风险区域。15号线设计时速140公里,分两期建设,二期全长约33公里,设11座车 站,开通后将缓解现有轨道线路客流压力,完善重庆市轨道交通网络。(央视新闻) ...