Workflow
10号线联络线工程
icon
Search documents
地铁亦庄线将与5号线直连直通
Bei Jing Wan Bao· 2025-10-23 06:43
Core Points - The Beijing Infrastructure Investment Company has announced the environmental impact report for the connection project between the Yizhuang Line and Lines 5 and 10, which is set to commence construction by the end of this year [2][5] - The project aims to directly connect the Yizhuang Line with Line 5 and facilitate transfers with Line 10, significantly improving transit efficiency and service levels [3][4] Project Details - The connection project will span approximately 2.7 kilometers, with 2.2 kilometers of new underground construction and 0.5 kilometers utilizing existing lines, all of which will be underground [2] - The construction methods will include shield tunneling, open-cut, and deep excavation, with no blasting operations involved [2] - The project will utilize B-type trains with a six-car configuration to maintain consistency with the existing lines [2] Expected Benefits - The project is expected to reduce the transfer passenger flow at Songjiazhuang Station by approximately 10,000 during peak hours, alleviating congestion [4] - An estimated 71,000 daily passengers will benefit from the direct connection, with 36,000 changing to same-platform transfers, reducing transfer distances by about 150 meters [4] - Overall, over 170,000 daily passengers will benefit from the project, accounting for approximately 88% of the total average daily transfer volume at the station [4] Timeline - The project is scheduled to be completed and operational by December 2028 [5]
北京这条地铁线开工在望
3 6 Ke· 2025-10-23 02:31
在北京轨道交通三期建设规划的各条线路中,亦庄线至5号线、10号线联络线虽然开启动作较晚,但进 展速度却很快。 近日,市发改委批复了亦庄线至5号线、10号线联络线工程项目的可行性研究报告,可研的批复是一项 工程开工前重要的环节,意味着这条线路距离开工已经不远了。 同时,京投公司官网今天也公示了亦庄线至5号线、10号线联络线工程的环评报告全文,其中表示,该 工程初步计划今年年底开工,2028年12月建成。 1 亦庄线目前是在宋家庄站与5号线、10号线三线换乘,因此宋家庄站也是北京轨道交通路网中换乘量最 大的车站之一。 但如果乘坐亦庄线想继续向北,那就要从亦庄线下车,换乘5号线。如果想去国贸、西三环等地,则要 下车换乘10号线。这多少都会给乘客带来不便。 而亦庄线至5号线、10号线联络线工程要解决的就是这个问题。 环评报告估算,在亦庄线和5号线贯通运营后,每天宋家庄站约7.1万人次可以不用再换乘。 而且由于10号线西向东方向与亦庄线、5号线贯通线的南向北方向是同台换乘的,因此3.6万人次将从原 来要步行150米换乘,改为了更便捷的同台换乘。整个宋家庄站日均将有17.1万人次的乘客因此受益, 占宋家庄站日均换乘总量约 ...
亦庄线至5号线10号线将建联络线
Core Points - The Beijing Infrastructure Investment Company has released the full environmental impact report for the connection line project between the Yizhuang Line and Lines 5 and 10, which is set to begin construction by the end of 2025 [2][3] - The project aims to directly connect the Yizhuang Line with Line 5 and facilitate same-platform transfers with Line 10, significantly improving transit efficiency and service levels [2][3] - The construction will cover approximately 2.7 kilometers, with 2.2 kilometers being newly constructed underground lines, and is expected to alleviate congestion at Songjiazhuang Station, which currently handles the highest transfer volume in the network [2][3] Project Details - The connection line will start from Xiaocun Station in Chaoyang District and end at Songjiazhuang Station in Fengtai District, with no new or expanded stations planned [2] - The project will utilize shield tunneling, open-cut, and underground excavation methods, avoiding blasting operations [2] - The implementation of this project is part of the third phase of Beijing's urban rail transit construction plan, which aims to enhance connectivity for the Yizhuang New Town with the central urban area [3] Expected Benefits - The project is projected to reduce the transfer passenger flow at Songjiazhuang Station by approximately 10,000 during peak hours, benefiting over 170,000 passengers daily, which accounts for about 88% of the average daily transfer volume [3] - The estimated changes include 71,000 passengers no longer needing to transfer, 36,000 passengers switching to same-platform transfers, and 65,000 passengers adjusting their transfer platforms, thus shortening transfer distances by about 150 meters and 100 meters respectively [3] - The completion of the project is anticipated by December 2028, pending official announcements from relevant government departments [3]
年底开工,地铁亦庄线将与5号线直连直通,为宋家庄站减压
Core Points - The Beijing Infrastructure Investment Company has released the Environmental Impact Report for the connection project between the Yizhuang Line and Lines 5 and 10, which is set to start construction by the end of 2025 [1] - The project aims to connect the Yizhuang Line directly with Line 5 and provide a transfer at the same platform for Line 10, significantly improving transit efficiency and reducing transfer times for passengers [4][5] Summary by Sections Project Overview - The connection project will span approximately 2.7 kilometers, with about 2.2 kilometers being newly constructed underground and 0.5 kilometers utilizing existing lines, all of which are underground [2] - The construction methods will include shield tunneling, open-cut, and deep excavation, with no blasting operations involved [2] Current Challenges - The existing Yizhuang Line does not provide direct access to the city center, and the 17th Line does not reach the core area of Yizhuang, highlighting the need for improved connectivity [2] - The Songjiazhuang Station is currently the only transfer point between Yizhuang New Town and the city center, experiencing high passenger flow and requiring urgent improvements [4] Expected Benefits - The project is part of the third phase of Beijing's urban rail transit construction plan, which will enhance service levels and efficiency of the subway system [4] - It is estimated that the project will reduce the transfer passenger flow at Songjiazhuang Station by approximately 10,000 during peak hours, alleviating congestion [4] - Daily, around 71,000 passengers will benefit from not needing to transfer, with 36,000 changing to same-platform transfers, and 65,000 adjusting their transfer stations, thus shortening transfer distances significantly [4]
亦庄线、5号线贯通改造年底开工,宋家庄站每天超7万人次免换乘
Xin Jing Bao· 2025-10-22 06:15
Core Viewpoint - The environmental impact report for the connection line project between Beijing's Yizhuang Line and Lines 5 and 10 has been successfully approved, with construction expected to start by the end of this year and completion projected for December 2028 [1][2]. Group 1: Project Overview - The project involves a connection line approximately 2.7 kilometers long, with 2.2 kilometers of new construction and 0.5 kilometers utilizing existing lines, all underground [2]. - The connection will allow direct operation between the Yizhuang Line and Line 5, and facilitate transfers with Line 10, enhancing connectivity in the region [1][3]. Group 2: Passenger Impact - The project is expected to eliminate the need for transfers for approximately 71,000 passengers daily at Songjiazhuang Station, which is currently the busiest transfer station in Beijing's rail network [3][4]. - The changes will reduce transfer pressure during peak hours by about 10,000 passengers each in the morning and evening [4]. Group 3: Operational Efficiency - The integration of the Yizhuang Line, Line 5, and Line 10 will lead to shared resources for vehicle maintenance and operations, optimizing resource allocation and reducing operational costs [5]. - The project aims to enhance the overall service level and efficiency of the subway system, improving the urban landscape of the area [5]. Group 4: Public Engagement and Environmental Concerns - During the public consultation phase, 27 individual opinions were collected, with concerns primarily focused on construction noise and vibration during operation [6]. - The environmental assessment includes measures to mitigate noise and vibration impacts, ensuring compliance with relevant standards [6].
地铁亦庄线与5号线贯通运营改造预计年底开工
Xin Jing Bao· 2025-07-16 10:59
Core Viewpoint - The Beijing Infrastructure Investment Company has announced the second public disclosure of the environmental impact assessment for the connection line project between the Yizhuang Line and Lines 5 and 10, which is set to start construction by the end of this year and be completed by June 2028 [1][4]. Group 1: Project Overview - The project aims to enhance the connectivity between the Yizhuang area and Beijing's central urban area, addressing significant passenger flow during peak hours, particularly at the Songjiazhuang station [2][6]. - The total length of the new connection line is approximately 2.7 kilometers, with about 2.2 kilometers being newly constructed and 0.5 kilometers utilizing existing lines, all of which will be underground [2][4]. Group 2: Construction Details - The construction will not involve new or expanded stations but will reserve space for a future station at Guojiazhuang Road, located between the Chengshousi Station of Line 10 and the Xiaocun Station of the Yizhuang Line [4][5]. - The project will be executed in two phases, with the first phase focusing on the connection between the Yizhuang Line and Line 5, and the second phase aiming for the connection with Line 10 [6]. Group 3: Future Implications - Once completed, the project will facilitate cross-line operations between the Yizhuang Line, Line 5, and Line 10, significantly improving commuting options for residents in the Yizhuang area [6].
亦庄线至5号线、10号线联络线环评公示
3 6 Ke· 2025-06-26 02:35
Core Viewpoint - The construction of the Yizhuang Line to connect with Line 5 and Line 10 is a significant development for residents in the southern region of Beijing, enhancing convenience and reducing transfer inconveniences at major interchange stations like Songjiazhuang [1][4]. Group 1: Project Overview - The Yizhuang Line to Line 5 and Line 10 connection project has begun its first environmental impact assessment (EIA) public announcement, indicating progress in the planning phase [1]. - The project will span approximately 2.7 kilometers, starting from the existing Xiaocun Station to Songjiazhuang Station [4]. - The initial EIA does not provide detailed route plans or diagrams, leaving the final route configuration uncertain until the second EIA [4]. Group 2: Operational Improvements - The project aims to facilitate through operation between the Yizhuang Line and Line 5, while optimizing transfers with Line 10, thereby improving overall passenger experience [5]. - The integration will occur in two phases: the first phase will align the signaling systems of the Yizhuang Line and Line 5, allowing for flexible train operations during peak hours to alleviate congestion at Songjiazhuang Station [5]. - The second phase will implement through operation with Line 10 once its equipment reaches the end of its service life, further enhancing connectivity [5].
环评启动,距地铁亦庄线与5号线实现跨线运营又近一步
Xin Jing Bao· 2025-06-25 09:26
Core Points - The Beijing Infrastructure Investment Company has announced the environmental impact assessment for the connection line project between the Yizhuang Line and Lines 5 and 10, which is approximately 2.7 kilometers long and aims to improve transportation connectivity between Yizhuang and the central urban area [1][2] - The Yizhuang Line currently experiences significant passenger flow, with nearly 200,000 daily riders, leading to congestion at transfer points, particularly at Songjiazhuang Station [1][2] - The project aims to facilitate direct operation between the Yizhuang Line and Line 5, as well as optimize transfers with Line 10, enhancing the commuting experience for passengers [2][3] Project Details - The connection line will run from the existing Xiaocun Station to Songjiazhuang Station, utilizing both new underground sections and existing lines to achieve operational connectivity [2] - The project is part of a broader plan to improve urban rail transit, with previous documents indicating a future goal of full operational integration among the Yizhuang Line, Line 5, and Line 10 [2] - Future steps will include line optimization and equipment upgrades to enable seamless operation between the Yizhuang Line and Line 10 [2][3]