POWERCHINA Ltd(601669)
Search documents
福建一水库大坝建设被指偷工减料!中国电建:全面调查核实
Zhong Guo Zheng Quan Bao - Zhong Zheng Wang· 2025-11-30 10:39
Group 1 - The core issue involves serious quality concerns regarding the construction of the Fujian Yong'an pumped storage power station, which is a key project under China's 14th Five-Year Plan for pumped storage [2][3] - China Power Construction Group (referred to as "the company") has established an investigation team to thoroughly investigate and verify the reported issues, and will handle the situation in accordance with laws and regulations [1][2] - The company appreciates the supervision from the public and will promptly disclose the results of the investigation [1] Group 2 - The construction of the lower reservoir of the Yong'an pumped storage power station, undertaken by the company's subsidiary, China Water Resources and Hydropower Third Engineering Bureau Co., Ltd. (referred to as "Water Resources Third Bureau"), has been accused of significant cost-cutting measures [2][3] - Reports indicate that hundreds of anchor piles used to reinforce the dam shoulder have serious quality defects, with actual construction lengths significantly shorter than required, and some piles being less than one-third of the design standard [3] - Additionally, most anchor piles were not constructed according to the required standards for cement and sand grouting, with the construction team only performing simple sealing at the pile openings to pass inspections [3]
新华每日电讯:水库大坝涉嫌偷工减料,质量红线不容触碰
Bei Jing Ri Bao Ke Hu Duan· 2025-11-30 08:48
Core Points - The construction of the Yong'an pumped storage power station's lower reservoir dam, undertaken by China Power Construction Corporation's subsidiary, has been reported to involve serious safety hazards due to alleged cost-cutting, violations of regulations, and arbitrary design changes [1][2] - A special investigation team has been established to address the significant safety concerns surrounding the dam, which is critical for withstanding extreme flooding [1][2] - The report highlights a broader issue of non-compliance in construction practices within the industry, as evidenced by a recent landslide incident at another project managed by a different subsidiary of China Power Construction [1] Industry Context - The Ministry of Water Resources has been tightening regulations to prevent substandard engineering practices, emphasizing a lifelong responsibility for quality in water conservancy projects [1] - The public is demanding timely and credible investigation results regarding the safety of major civil engineering projects, reflecting a growing concern for infrastructure integrity [2] - There is a call for strict penalties against those responsible for compromising safety standards, aiming to deter future violations in the industry [2]
水库大坝涉嫌偷工减料 质量红线不容触碰
Xin Lang Cai Jing· 2025-11-30 08:33
Core Viewpoint - The article highlights serious allegations against China Power Construction Corporation's subsidiary, Hydro Power Third Bureau, regarding the construction of the Yongan Pumped Storage Power Station's reservoir dam in Fujian Province, which is suspected of quality violations and safety risks [1] Group 1: Allegations and Investigations - The construction of the Yongan Pumped Storage Power Station's reservoir dam is under scrutiny for potential cost-cutting measures, non-compliance with regulations, and arbitrary design changes, posing significant safety hazards [1] - A special investigation team has been established to look into the allegations surrounding the dam's construction [1] - The article references a previous incident involving another subsidiary, Hydro Power Sixteenth Bureau, which experienced a significant landslide in August during a similar project, indicating a pattern of unsafe practices [1] Group 2: Regulatory Context and Public Concerns - The Ministry of Water Resources has implemented strict regulations, including a lifelong responsibility system for water conservancy project quality, to prevent substandard engineering practices [1] - The article emphasizes the importance of addressing potential risks and ensuring safety in major public works, urging authorities to provide credible investigation results to the public [1] - There is a call for severe penalties against those responsible for compromising dam safety, to deter future violations and protect public interests [1]
福建75亿元项目水库大坝被指偷工减料,中国电建深夜通报:全面调查核实!
Di Yi Cai Jing· 2025-11-30 06:58
Core Viewpoint - China Power Construction Group (China Power) has acknowledged serious quality issues in the construction of the Yong'an Pumped Storage Power Station and has established an investigation team to address these concerns and ensure compliance with regulations [1][4]. Group 1: Quality Issues - Reports indicate that the construction of the lower reservoir at the Yong'an Pumped Storage Power Station has been criticized for significant cost-cutting measures [4]. - The project, undertaken by subsidiaries of China Power, has revealed severe quality defects in the hundreds of anchor piles used for reinforcing the dam shoulder, with actual lengths significantly shorter than the design specifications [5][8]. - Many anchor piles were not constructed according to the required standards, with some being less than one-third of the specified length, and inadequate cement grouting was performed [5][8]. Group 2: Construction Practices - Experts have highlighted that the stability of the dam is critically dependent on the integrity of the anchor piles, which are essential for reinforcing the dam's slope [7]. - The design specifications required a complete structure for the anchor piles, but many were only connected using simple "spot welding," failing to meet the necessary structural integrity [7][8]. - On-site workers reported that the actual lengths of some anchor piles were as short as 2 to 5 meters, with significant discrepancies in the lengths of the reinforcing steel bars [8][9]. Group 3: Oversight and Accountability - Concerns have been raised regarding the oversight of the project, as the supervising entity is a subsidiary of the same parent company responsible for the design and construction, leading to questions about accountability [9]. - Reports of inappropriate conduct among monitoring personnel, including accepting entertainment from the construction team, have surfaced, raising further doubts about the integrity of the oversight process [11]. - The Yong'an Pumped Storage Power Station project has a total investment of 7.5 billion yuan, with expected annual power generation of 12.6 billion kilowatt-hours, contributing to significant carbon reduction and economic benefits [11].
75亿大坝建设被曝偷工减料 监理接受有偿异性陪侍
Jing Ji Guan Cha Wang· 2025-11-30 05:17
Core Viewpoint - China Power Construction Group (China Power) is facing serious allegations regarding construction quality issues at the Fujian Yong'an Pumped Storage Power Station, which is a key project under the national "14th Five-Year Plan" for pumped storage. The company has established a special investigation team to address these concerns and ensure compliance with legal and regulatory standards [2][5]. Group 1: Project Overview - The total investment for the Fujian Yong'an Pumped Storage Power Station is 7.5 billion yuan, making it the first approved large-scale energy storage project in Fujian Province under the "14th Five-Year Plan" [3]. - Upon completion, the project is expected to generate an average annual electricity output of 12.6 billion kilowatt-hours, saving 660,000 tons of standard coal and reducing carbon dioxide emissions by 1.65 million tons, with a carbon reduction benefit of 153 million yuan and tax revenue of 180 million yuan [3]. Group 2: Quality Issues - Investigations revealed severe quality defects in the hundreds of anchor piles used to reinforce the dam shoulder, with some piles measuring less than one-third of the required 12 meters, and only one or two out of three steel bars meeting the standard length [3][4]. - Reports indicate that only about 30% of the anchor piles meet design requirements, with many being classified as "substandard" due to inadequate cement and sand filling, posing a direct threat to the dam's overall safety [4]. Group 3: Supervision and Corruption Concerns - The incident has highlighted significant supervisory failures, with reports of monitoring personnel from Zhejiang Huadong Engineering Consulting Co., Ltd. accepting entertainment from the construction party, raising questions about the integrity of the oversight process [5]. - The monitoring unit's failure to fulfill its supervisory role and its potential collusion with the construction party has sparked public concern regarding corruption and the effectiveness of the monitoring system [5][6]. Group 4: Investigation and Future Implications - An investigation team led by senior management has been established to conduct a thorough review of project management, financial processes, procurement, and safety production [6]. - The incident not only impacts China Power's brand image and industry reputation but also serves as a warning for the construction industry to prioritize quality and safety over speed and economic benefits, addressing issues of corruption and regulatory compliance [6].
媒体曝光75亿元项目“严重偷工减料”!中国电建:已成立调查组
Sou Hu Cai Jing· 2025-11-30 04:18
Core Viewpoint - China Power Construction Corporation (China Power) has acknowledged quality issues in the construction of the Yong'an pumped storage power station and has established an investigation team to address these concerns and ensure compliance with regulations [1]. Group 1: Project Overview - The Yong'an pumped storage power station has a total investment of 7.5 billion yuan and is the first large-scale energy storage project approved under Fujian Province's 14th Five-Year Plan [1]. - The project involves the construction of a lower reservoir dam, which has reportedly faced serious quality issues during construction [1]. Group 2: Quality Concerns - Reports indicate that hundreds of anchor piles used to reinforce the dam's shoulder have significant quality defects, with actual construction lengths being substantially shorter than required, with some piles being less than one-third of the design specifications [1]. - Many of the anchor piles were not constructed according to the required standards for cement and sand filling, with the construction team only performing minimal sealing at the pile openings to pass inspections [1]. - According to design requirements, over 1,000 anchor piles need to be installed on both sides of the dam's shoulder, with more than 600 completed; however, workers estimate that only about 30% of these piles meet the design standards, while the majority are considered substandard [1].
福建一水库大坝施工被指“严重偷工减料”,中国电建深夜通报
Bei Jing Qing Nian Bao· 2025-11-30 03:59
Group 1 - The core issue involves serious quality problems reported during the construction of the Yongan pumped storage power station in Fujian, specifically regarding the dam construction [4] - China Power Construction Group has established an investigation team to thoroughly investigate and verify the reported issues, and will handle the situation according to laws and regulations [2] - The construction is being carried out by subsidiaries of China Power Construction, specifically the Hydropower Third Bureau and the Hydropower Sixteenth Bureau [4] Group 2 - Reports indicate that hundreds of anchor piles used to reinforce the dam shoulder have significant quality defects, with actual construction lengths significantly shorter than required, with some piles being less than one-third of the design standard [4] - Many anchor piles were not filled with cement mortar as per the required standards, with the construction team only performing simple sealing at the pile openings to pass inspections [4]
福建永安一水库大坝施工被指偷工减料!中国电建称将调查核实
Nan Fang Du Shi Bao· 2025-11-30 03:13
Group 1 - The construction of the lower reservoir for the Fujian Province Sanming City Yong'an Pumped Storage Power Station has been accused of serious quality issues, including significant cost-cutting measures during dam construction [2] - Reports indicate that hundreds of anchor piles used to reinforce the dam shoulder have severe quality defects, with actual lengths significantly shorter than designed, and some piles being less than one-third of the required length [2] - The construction company, China Water Resources and Hydropower Third Engineering Bureau Co., Ltd., is under scrutiny, and China Power Construction Group has established an investigation team to address the reported issues [2][3] Group 2 - The total investment for the Yong'an Pumped Storage Power Station project is approximately 7.5 billion yuan, making it the first large-scale energy storage project approved under Fujian Province's 14th Five-Year Plan [3] - The lower reservoir dam features a concrete-faced rock-fill design, with a height of 102.5 meters, a top elevation of 483 meters, and a top length of 267.5 meters, making it the tallest concrete-faced rock-fill dam approved in Fujian Province [3]
中国电建连夜通报:已成立调查组
券商中国· 2025-11-30 02:06
Group 1 - The core viewpoint of the article is that China Power Construction Group has taken the allegations of quality issues at the Fujian Yong'an pumped storage power station seriously and has established an investigation team to address these concerns [1] - The Fujian Yong'an pumped storage power station is a key project under the national pumped storage initiative for the 14th Five-Year Plan, highlighting its significance in the energy sector [1] - Reports indicate that there are serious allegations of cost-cutting measures during the construction of the dam at the lower reservoir of the power station, raising concerns about the integrity of the project [1]
中国电建深夜通报!
中国能源报· 2025-11-30 01:50
Core Viewpoint - China Power Construction Corporation (中国电建) is taking the allegations of quality issues at the Fujian Yong'an pumped storage power station seriously and has established an investigation team to address the concerns raised by the media [2][5]. Group 1: Investigation and Response - The company has formed an investigation team to conduct a comprehensive investigation and verification of the reported quality issues at the construction site [2]. - China Power Construction Corporation expresses gratitude for the public's supervision and commits to timely disclosure of the investigation results [2]. Group 2: Project Details and Allegations - The Fujian Yong'an pumped storage power station is a key project under the national pumped storage initiative for the 14th Five-Year Plan [5]. - Reports indicate that there are serious quality defects in the construction of the dam, specifically regarding the anchoring piles used to reinforce the dam shoulder slope [5]. - It has been noted that the actual construction length of the hundreds of anchoring piles is significantly shorter than required, with some piles being less than one-third of the design standard [5]. - Additionally, many anchoring piles were not constructed according to the required standards for cement and sand slurry infusion, with the construction team only performing minimal sealing at the pile openings to pass inspections [5].