广东电白抽水蓄能工程进入机电安装阶段
Ren Min Ri Bao· 2026-02-09 19:01
Core Viewpoint - The Guangdong Electric Power Storage Project has reached a significant milestone with the completion of underground excavation, marking the transition to the electromechanical installation phase, which is expected to enhance clean energy development in the region [1] Group 1: Project Details - The project is located in the deep mountains of western Guangdong, featuring giant wind turbine blades and significant construction activity [1] - The underground plant, situated 100 meters deep, will house four units of 300,000 kilowatts each, capable of converting 1.26 million cubic meters of water into 1.2 million kilowatt-hours of clean electricity per hour [1] - The project is part of China's medium- to long-term plan for pumped storage hydropower, with an expected operational date for all units in the first half of 2028 [1] Group 2: Environmental Impact - Upon completion, the power station is projected to reduce carbon emissions equivalent to planting 120,000 trees annually [1] - The facility is expected to consume 2.16 billion kilowatt-hours of clean energy each year, ensuring stable delivery of clean power in western Guangdong [1] Group 3: Technological Innovations - The project has implemented 3D visualization safety monitoring technology to strictly control excavation parameters and operational indicators [1] - This technological advancement is aimed at enhancing safety and efficiency during the construction phase [1]
新春走基层丨5G赋能智慧绿电 辽宁移动助力清原抽水蓄能电站建设
Xin Lang Cai Jing· 2026-02-09 12:03
Core Insights - The construction of the Guoneng Xinyuan Liaoning Qingyuan Pumped Storage Power Station, with a total installed capacity of 1.8 million kilowatts, is a key project in China's energy strategy, expected to generate 3 billion kilowatt-hours annually, saving 158,000 tons of standard coal and reducing carbon dioxide emissions by 375,000 tons, thus supporting the "dual carbon" goals [1] Group 1: Project Overview - The power station will serve as a stabilizer for the Northeast power grid, facilitating peak shaving and frequency modulation while contributing to green transformation [1] - The project is positioned as a "super green power charging treasure" and is crucial for the implementation of national energy strategies [1] Group 2: Technological Integration - Liaoning Mobile has successfully implemented a 5G private network project in collaboration with the power station, enhancing operational intelligence and ensuring data security with a customized solution [2] - The 5G network features a three-tier model ("Enjoy, Exclusive, Respect") to meet the stringent requirements for data confidentiality and low latency [2] Group 3: Communication Challenges and Solutions - The construction site faced significant communication challenges due to complex geological conditions, leading to signal coverage issues in four construction tunnels [4] - Innovative solutions included the use of a "700M + reverse 900M frequency band combination" to optimize signal paths and the establishment of local computing nodes for future AI applications [4] Group 4: Operational Support - The core construction area was previously a communication blind spot, with no mobile signal or broadband coverage, complicating equipment transport and operations [5] - Liaoning Mobile addressed these challenges by employing a hybrid power supply model and forming a dedicated support team to ensure continuous communication for construction workers [5] Group 5: Future Prospects - The company plans to deepen the integration of new technologies like 5G-A and AI with the energy sector, expanding the "5G + Smart Power" application scenarios [5] - This initiative aims to provide robust communication networks for major green energy projects, contributing to the revitalization of Northeast China and supporting the national "dual carbon" objectives [5]
深圳抽蓄电站累计发出绿电突破百亿千瓦时
中国能源报· 2026-02-06 09:58
深蓄电站规划建设充分利用了深圳原有盆地、水库的自然资源优势,结合城市地貌建 设电站,开创了我国把抽蓄电站建在城市中心的"先河"。电站建成后,建设运维者 们通过植树造林、设立体验展区、开展开放日活动等举措,把深蓄电站打造为深圳市 集电力调节、休闲踏青、科普参观为一体的绿色能源"新地标",累计向200多万市民 免费开放。 2 月 3 日 , 我 国 首 个 建 在 城 市 中 心 的 抽 水 蓄 能 电 站 —— 南 网 储 能 公 司 深 圳 抽 水 蓄 能 电 站,投产以来累计发出绿电突破百亿千瓦时。该电站以高质量运行增强深圳电力可靠韧 性,促进绿色低碳美丽城市建设。 深蓄电站安装4台同时具有"抽水"和"发电"功能的30万千瓦机组。当城市用电负荷低 谷时,利用机组抽水功能,把下水库的水抽至上水库储能;用电负荷高峰时,放上水 库的水到下水库,利用机组发电功能为深圳供电,实现水能和清洁电能按照城市电力 需要灵活转换。"电站调节能力接近深圳最高电力负荷的1 / 8 ,用电高峰时段可满足120 万台家用空调同时开启的负荷调节需求。仅2025年,电站就启动超过4 0 0 0次,同比 增长12%,创历史新高。"南方电网储 ...
我国首个城市中心抽蓄电站累计发电量破百亿
Zhong Guo Dian Li Bao· 2026-02-06 03:47
Core Insights - The Shenzhen Pumped Storage Power Station, the first of its kind in an urban center in China, has generated over 10.32 billion kilowatt-hours of green electricity since its commissioning [1] - The power station has a total installed capacity of 1.2 million kilowatts and was fully operational in September 2018 [1] - The generated electricity is equivalent to the annual power consumption of 4.5 million residents in Shenzhen [1] Summary by Categories Capacity and Functionality - The Shenzhen Pumped Storage Power Station is equipped with four 300,000-kilowatt units that can both pump water and generate electricity [1] - During low electricity demand periods, the station pumps water from a lower reservoir to an upper reservoir for energy storage [1] - During peak demand, it releases water from the upper reservoir to generate electricity, thus providing flexible energy conversion based on urban electricity needs [1] Operational Performance - The station's regulation capacity is close to one-eighth of Shenzhen's maximum electricity load, capable of meeting the demand of 1.2 million household air conditioners during peak times [1] - In 2025, the station is expected to operate over 4,000 times, marking a 12% year-on-year increase and setting a historical record [1]
市政协十五届六次会议委员向大会报到
Xin Lang Cai Jing· 2026-02-04 15:22
转自:承德发布 "这份提案打磨了一个多月,就盼着在会上好好交流""今年想重点聊聊产业融合的事儿",刚完成报到流程,委员们便三五成群围坐交流,话题紧紧围绕生 态保护、产业升级、民生改善等核心议题,字里行间满是对承德高质量发展的深切关切与责任担当。 市政协十五届六次会议委员向大会报到 春潮涌动催奋进,履职尽责赴盛会。2月4日上午,承载着全市人民的殷切期盼,肩负着参政议政的神圣使命,出席市政协十五届六次会议的委员们陆续抵 达驻地,向大会报到。一张张充满干劲的脸庞、一句句关乎发展的热议,让承德正式进入凝心聚力、共话发展的"两会时间"。 核验信息、签到登记、领取会议资料、佩戴委员证……报到现场秩序井然,工作人员早已做好充分准备,以高效便捷的服务引导委员们完成各项手续。来 自各行各业、各界别的366名市政协委员,带着深入基层调研的成果与思考,步履从容、精神饱满,迅速融入浓厚的履职氛围中。 承德日报社记者/李亚冰、闫明,摄影/王立群、张雨樵 "民生保障与城市治理是提升群众幸福感的关键抓手。"市政协委员、承德晨阳汽配城总经理聂树国带来了关于"持续深化民生保障提质赋能城市治理现代 化"的提案。他表示,要以更精准的举措补短板,以 ...
能源绿色低碳转型”看山东之国网新源泰山抽水蓄能:守护电网安全,助建“储能之都
Zhong Guo Fa Zhan Wang· 2026-02-04 06:31
Core Viewpoint - The Shandong Taishan Pumped Storage Co., Ltd. is advancing multiple pumped storage projects to enhance energy efficiency and contribute to carbon reduction goals in Shandong Province [1][2][3] Group 1: Company Overview - Established in 1999, Shandong Taishan Pumped Storage Co., Ltd. has a registered capital of 2.60081 billion RMB, with investments from State Grid Xinyuan Group (50.29%), State Grid Shandong Electric Power Company (43.39%), and Taishan Investment Co., Ltd. (6.32%) [1] - The company manages two pumped storage power stations: the first phase with a total investment of 4.3 billion RMB and a capacity of 1 million kW, and the second phase with a planned investment of 10.748 billion RMB and a capacity of 1.8 million kW [1][2] Group 2: Project Details - The first phase of the Taishan pumped storage power station has been operational since June 2007, achieving an average of over 3,000 starts per year, and saving 434,000 tons of standard coal and 255,000 tons of fuel annually [1] - The second phase is designed to generate 1.8 billion kWh annually and pump 2.4 billion kWh, with a focus on domestic technology breakthroughs in variable-speed units [2] - The third phase, with a total investment of 2.6 billion RMB and a capacity of 450,000 kW, is expected to start construction during the 14th Five-Year Plan period and be completed by 2033 [3] Group 3: Environmental Impact - The second phase of the project is projected to save 784,000 tons of standard coal annually and reduce emissions of CO2 by 1.3 million tons, SO2 by 28,700 tons, and NOx by 3,300 tons [2] - The company aims to contribute to the establishment of a "green and low-carbon energy transition demonstration zone" in Shandong Province, aligning with national carbon peak and carbon neutrality goals [3]
广发证券:容量电价日臻完善 新型储能核心受益
智通财经网· 2026-02-03 03:31
智通财经APP获悉,广发证券发布研报称,新型储能经济性改善,火电盈利稳定性提升,抽蓄稳中提 质。2026年我国新型储能需求有望保持高景气增长,有望带动储能产业链各环节盈利的改善,推荐储能 电池及材料龙头企业。具有选址、运营优势的龙头集成企业有望实现储能电站更高收益率并提高市占 率。电力交易能力有望成为储能电站运营的核心壁垒。 近年来,我国在电力市场化改革过程中持续强化对容量电价机制建设的政策引导。2026年1月30日,国 家发展改革委、国家能源局发布《关于完善发电侧容量电价机制的通知》(发改价格〔2026〕114号), 强调:分类完善煤电、天然气发电、抽水蓄能、新型储能容量电价机制,优化电力市场机制,通过"保 底工资"的制度性安排,推动相关电源顶峰时发电保供,有力促进新能源消纳利用;容量电价新政亦首次 明确可靠容量补偿标准确定原则,有望从"分类补偿"有序扩展至"同工同酬",推动各类调节性电源的公 平竞争。此外,多省区率先发布落地政策:内蒙古与新疆实行储能放电量补偿,较难动态反映容量供 需;河北容量补偿未建立容量补偿设定标准,本质为固定式补偿;甘肃、青海与宁夏三地在容量电费的计 算方法上统一采用了"有效容量×容 ...
中信证券:容量电价带来收益高确定性 有望明显带动国内储能装机
Zhi Tong Cai Jing· 2026-02-03 01:26
Core Viewpoint - The implementation of the national capacity pricing policy for energy storage is expected to stabilize revenue expectations and stimulate investment enthusiasm among owners, which is significant for investment decisions by state-owned enterprises and other clients [1][7]. Group 1: Capacity Pricing Mechanism - The new capacity pricing mechanism categorizes and improves the pricing for coal, natural gas, pumped storage, and new energy storage, ensuring reasonable pricing for regulatory capacity [2][9]. - The document mandates that the proportion of fixed cost recovery through capacity pricing for coal power plants be raised to no less than 50% by 2026, with potential for further increases based on local market conditions [10]. - For new energy storage, local governments can provide capacity pricing for independent energy storage stations that do not participate in mandatory storage, which will be included in local system operating costs [2][12]. Group 2: Economic Impact and Growth Projections - The capacity pricing is expected to provide high revenue certainty, significantly boosting domestic energy storage installations, with projections indicating a growth rate of 84% year-on-year for new energy storage installations in 2025, reaching 183 GWh [5][6]. - The establishment of the capacity pricing mechanism is anticipated to enhance the investment return rate for projects, increasing from 4.1% to 6.3% with a capacity price of 55 yuan/kW [5][4]. - The capacity pricing policy is seen as a critical support for the independent development of energy storage, transitioning the industry from cost competition to value creation [1][7]. Group 3: Industry Dynamics and Competitive Landscape - The introduction of a reliability capacity compensation mechanism will strengthen assessments and encourage owners to improve the quality of energy storage products, benefiting high-quality products and promoting industry consolidation [6][7]. - The policy changes are expected to lead to a rational return of investment in the pumped storage sector, with new projects relying more on actual market demand [11][13]. - The energy transition is supported by the development of regulatory power sources, which will help alleviate downward pressure on electricity prices and enhance the absorption of renewable energy [9][13].
中信证券:煤核短期受冲击,抽蓄分化,储能迎支撑
Jin Rong Jie· 2026-02-03 01:06
Core Viewpoint - The article highlights the improvements in the capacity mechanism for power generation, which promotes the development of adjustable power sources and facilitates the consumption of renewable energy [1] Group 1: Capacity Mechanism and Pricing - The capacity pricing for coal power is being enhanced while the long-term price floor is being relaxed, which may lead to downward pressure on comprehensive sales prices in regions with excess capacity [1] - The significant changes in the pumped storage pricing mechanism will result in new pumped storage projects relying more on the actual demand in the local electricity market for revenue generation [1] Group 2: Impact on Energy Sources - The introduction of capacity pricing policies is expected to be a crucial support for the independent development of energy storage [1] - The potential further decline in long-term electricity prices for thermal power in certain provinces may impact the nuclear power market prices in those areas [1] - The development of adjustable power sources is beneficial for enhancing the consumption of renewable energy and alleviating downward pressure on electricity prices [1]
抽水蓄能概念走强 顺纳股份、杭电股份涨停
Shang Hai Zheng Quan Bao· 2026-02-02 11:04
Core Viewpoint - The pumped storage concept is gaining strength in the market, with several companies experiencing significant stock price increases on February 2nd [1] Group 1: Company Performance - ShunNa Co., Ltd. (000533) saw its stock price rise to 9.22, with a gain of 10.02% [1] - Hangdian Co., Ltd. (603618) reached a stock price of 9.94, reflecting a 9.96% increase [1] - American Technology (688676) achieved a stock price of 97.85, marking a 6.92% rise [1] - Shenling Environment (301018) recorded a stock price of 68.78, with a 4.98% increase [1] - Southern Power Storage (600995) had a stock price of 14.18, up by 4.65% [1] - Guodian Nanzi (600268) reached a stock price of 13.34, reflecting a 4.38% increase [1] - XJ Electric (000400) saw its stock price at 31.10, with a 4.26% rise [1] Group 2: Market Trends - The early morning of February 2nd witnessed a strong performance in the pumped storage sector, with stocks like ShunNa and Hangdian hitting the daily limit [1] - Other companies such as Jinpan Technology and Shenling Environment also experienced upward movement in their stock prices [1]